Page 40 - ArchDC_Summer 2020
P. 40

Second floor meeting spaces.

            “Innovation” may be exciting, but often the work   Co|Lab project. “There was a lot of internal angst at
        to make it happen is far from glamorous. Sometimes   HITT, with people saying, ‘We don’t typically do things
        the paperwork alone can be daunting. For example,   this way, why are we doing this?’ There were a lot of
        WM+P’s Projects Materials Table, which tracks how the   coming-together moments when people needed to
        building’s materials perform relative to the criteria of   be re-inspired.”
        the Living Building Challenge, has some 2,000 rows      In fact, on day one of construction at the Co|Lab
        listing the materials, and 35 columns of criteria for   site, the first major item to be installed—underslab
        each. Not every cell requires an input, but compiling   piping—required a corrective. Polypropylene piping
        that much data is a substantial task. This table covers    was specified, but initially the much more common
        only the materials actually selected, not the innumerable    (but unfortunately, toxic-byproduct-producing) PVC
        ones that were considered but ultimately rejected.   was provided. Architect Reilly noted, wryly, “We have
            Moreover, finding optimized materials is only part   to say ‘No’ an awful lot.”
        of the puzzle. Once selected, they must also perform      There was little precedent for this facility. Over time,
        properly—and provably—as components of assemblies.   the architects and client settled on a double-height
        Even in a high-budget project like Co|Lab, costs are   flexible-use space to house prototypes and experiments,
        almost always a big stumbling block, particularly   with associated meeting and brainstorming areas.
        since in this case “proprietary specifications” were   HITT had previously received approval from Fairfax
        necessary for many elements (that is, only one product,   County for an employee fitness center on the site; the
        by one manufacturer, was acceptable, dampening the   company didn’t want to rehash the approval process,
        competitive bidding process that is generally held to   so the footprint and height couldn’t shift much.
        keep prices in check). Once construction commences,   Fortuitously, as a result of site constraints, the basic site
        the architect must become an enforcer and an inspirer.  plan—an east-west orientation with most of the glazing
            HITT has constructed over 170 LEED-certified   on the south side—was ideal for the passive solar
        projects. Nevertheless, pushing into a deeper level of   aspect of sustainable design.
        sustainability was not easy. “It’s a learning process for      Cross-laminated timber (CLT) was quickly settled
        everyone involved, including us,” commented Alastair   upon as the primary building material because of its
        Reilly, AIA, LEED AP, design partner at WM+P for the    substantial carbon-positive characteristics combined
        38                     IT’S NOT EASY BEING GREEN
   35   36   37   38   39   40   41   42   43   44   45